Drilled Shafts...Oscillator/Rotator Shafts...Conventional Shoring...Pre-drilled/Vibrated Piles...Tieback & Tiedown Anchors...Soil Nailing/Vnail Systems...Temporary & Permanent Shotcrete...Sculptured Shotcrete...Secant Pile Walls...Cylinder Pile Walls...Access Shafts...Micropiles...Augercast Piles...Drilled Displacement Piles...Deep Soil Mixing...Cutter Soil Mixing...Jet Mixing...Jet Grouting...Compaction Grouting...Chemical Grouting...Vibro Compaction...Stone Columns...Aggregate Piers...Dynamic Deep Compaction...Dewatering.
CUTTER MIX WALLS

635 Elliott Street, Seattle, WA

Malcolm Drilling was originally approached to budget a Secant shoring wall to Lease Crutcher Lewis for owner Martin Selig Real Estate at 635 Elliott St Seattle.

Preliminary budgetary pricing for the Secant Wall exceeded the owner’s allotment for shoring.

Malcolm Drilling provided the owner with a Value Engineering solution to the original shoring concept which resulted in a savings to the owner of $ 1,500,000. This revised concept utilized CSM ( Cutter Soil Mixing ) techniques to provide a continuous secant wall for the shoring system.

Malcolm Drilling worked diligently with the construction and design team to design and launch the first permanent CSM wall in the State of Washington.

 

 