Drilled Shafts...Oscillator/Rotator Shafts...Conventional Shoring...Pre-drilled/Vibrated Piles...Tieback & Tiedown Anchors...Soil Nailing/Vnail Systems...Temporary & Permanent Shotcrete...Sculptured Shotcrete...Secant Pile Walls...Cylinder Pile Walls...Access Shafts...Micropiles...Augercast Piles...Drilled Displacement Piles...Deep Soil Mixing...Cutter Soil Mixing...Jet Mixing...Jet Grouting...Compaction Grouting...Chemical Grouting...Vibro Compaction...Stone Columns...Aggregate Piers...Dynamic Deep Compaction...Dewatering.

Peach Arch Design/Build Project
Border Crossing at Blaine, WA

Malcolm Drilling constructed the shafts for the Northbound I-5 Peace Arch Border Crossing project in Blaine, WA in 2008 utilizing oscillator equipment. 12EA 2.2M diameter shafts were constructed by advancing temporary oscillator casing with a 2.5M oscillator attached to a Liebherr 883 dig crane excavating the shafts to a depth of 170’. MDCI also hoisted and placed the long resteel cages as single units that had been coupled horizontally on the ground prior to hoisting. As the shaft concrete was pumped, a 12’ long permanent slip-in casing was placed inside of the oscillator casing to facilitate placement of the concrete in the column transition zone (by the General Contractor).

MDCI also constructed 11EA 1.2M diameter abutment shafts on the Peace Arch project with a Bauer BG-40 drill rig hard coupled to a 2M oscillator. These shafts were advanced to a depth of 130’ with concrete placed to the surface elevation since these shafts were used for the bridge abutments.

 

 
Terms of Use | Privacy Statement © 2011 Malcolm Drilling Co., Inc. All rights reserved