Drilled Shafts...Oscillator/Rotator Shafts...Conventional Shoring...Pre-drilled/Vibrated Piles...Tieback & Tiedown Anchors...Soil Nailing/Vnail Systems...Temporary & Permanent Shotcrete...Sculptured Shotcrete...Secant Pile Walls...Cylinder Pile Walls...Access Shafts...Micropiles...Augercast Piles...Drilled Displacement Piles...Deep Soil Mixing...Cutter Soil Mixing...Jet Mixing...Jet Grouting...Compaction Grouting...Chemical Grouting...Vibro Compaction...Stone Columns...Aggregate Piers...Dynamic Deep Compaction...Dewatering.
EXCAVATION SUPPORT

SR-519 Project, Seattle, WA

The State Route 519 is a crucial connection from I-5 and I-90 to the waterfront for cars and freight. The project will rechannel, widen and improve the First Avenue and South Atlantic Street intersection in Seattle. An elevated ramp will be constructed that connects westbound I-90 to the South Atlantic Street overpass and rechannel South Royal Brougham Way Railroad Overpass between Fourth Avenue South and First Avenue South. In addition, they will close the at-grade Burlington Northern Santa Fe (BNSF) railroad crossing on South Royal Brougham Way and construct a grade separating structure that will cross over the BNSF railroad tracks and connect Third Avenue South to South Royal Brougham Way Railroad Overpass.

For this project Malcolm constructed 26 total large diameter oscillator fully cased drilled shafts along Royal Brougham and Atlantic Street in Seattle. Along Royal Brougham 10 total 2.8 meter shafts were installed to depths in upwards of 100 feet deep. 5 total 4 foot OD shafts by 70 feet long were also installed along Royal Brougham for their parking and stairway structures. Along Atlantic Street 11 total 3 meter shafts were installed in upwards of 100 feet deep. Permanent slip in casing shoring ranging from 20 feet to 38 feet long was also installed in all shafts along Royal Brougham and Atlantic Street to facilitate the General Contractors column transition pours.

5 drilled shafts along Royal Brougham were installed directly in between (within inches) of a live 72 in water main and a live 96 in sewer main. The utilities were between 4 feet and 7 feet below ground. These utilities were still in use so it was crucial that no damage was done while we were constructing the drilled shafts at these locations. The 3 meter oscillator is capable of producing a maximum of 1.8 million foot pounds when extracting the temp casing, so to ensure we did not crush or damage the two utilities while installing the shafts we installed 4 micro piles at each location, each being 8 in OD by 90 feet in length. After the micro pile installation was complete we set a steel reaction frame on the micro piles. Our oscillator was then set on top of the reaction frame. By doing this we able to displace the weight of the equipment and the reaction force of the oscillator below the utilities thus ensuring that no damage was done.

 

 
Terms of Use | Privacy Statement © 2010 Malcolm Drilling Co., Inc. All rights reserved