Drilled Shafts...Oscillator/Rotator Shafts...Conventional Shoring...Pre-drilled/Vibrated Piles...Tieback & Tiedown Anchors...Soil Nailing/Vnail Systems...Temporary & Permanent Shotcrete...Sculptured Shotcrete...Secant Pile Walls...Cylinder Pile Walls...Access Shafts...Micropiles...Augercast Piles...Drilled Displacement Piles...Deep Soil Mixing...Cutter Soil Mixing...Jet Mixing...Jet Grouting...Compaction Grouting...Chemical Grouting...Vibro Compaction...Stone Columns...Aggregate Piers...Dynamic Deep Compaction...Dewatering.

Tanana River Bridge #505, Tok, Alaska

Malcolm Drilling furnished and installed 10’ diameter permanent steel casing at five (5) shaft locations with Leffer 3050 oscillator equipment on this project: one pier location was on land, two were installed on a sand island constructed in the river, and two were installed from a work trestle and finger piers constructed over the river. Permanent steel casing segments were welded together vertically over the shaft location with the deepest casing installed at a length of 176’ - the deepest shaft in Alaska history. A Liebherr 885 dig crane excavated the shafts utilizing a 3M spherical grab, dumping shaft sands and gravels into waiting dump trucks. Four of the shaft locations feature rock sockets up to 39’ deep below the permanent casing. MDCI placed all reinforcing steel cages as single units and then furnished and placed 4000P shaft concrete in all shafts.

Malcolm also furnished and installed four (4) 4’ diameter permanent steel casings at Abutment 1 that were slipped inside of temporary oscillator casing. A 1.5M oscillator was hard coupled to a Bauer BG-40 top drive drill rig that was utilized to remove the shaft material from within the temporary casing. After the casings were excavated, permanent casing segments were hoisted and welded over the shaft, the temporary oscillator casing was extracted, the reinforcing steel cages were placed and the shaft concrete was pumped into the permanent casings.

In addition, six (6) 30” diameter shafts were drilled in rock at Abutment 7 with the Bauer BG-40 drill rig to a depth of 52’.

 

 
Terms of Use | Privacy Statement © 2010 Malcolm Drilling Co., Inc. All rights reserved