Drilling Deeper

Oceanwide Center Update

Malcolm recently completed the installation of one method and two full scale load test shafts. All shafts were drilled into bedrock with the deepest hole reaching 324 feet below grade. Multi-level Bi-directional testing was successfully performed to a maximum equal top load of over 24,000 kips. Test data will be used to confirm or adjust previous design values for this design-assist project. CSM test panel installation will be next before we continue with the construction of the temporary shoring wall on this very challenging project in the middle of San Francisco.