The Foundation for Miami’s E11EVEN Residences Beyond: Deep Soil Mixing and CFA Piles
Rising above Miami’s iconic club district, the E11EVEN Residences Beyond tower is a striking new addition to the downtown skyline. Malcolm provided a specialized deep foundation system for the 65-story, 700-foot skyscraper.
Malcolm employed the deep soil mixing (DSM) method, treating over 15,000 square feet of area to facilitate deep excavation without the need for dewatering. A total of 150 tons of steel were used to support the cantilever walls of the excavation.
Malcolm performed chemical grouting to underpin the neighboring buildings to stabilize them during the foundation work.
Nearly 10,000 cubic yards of grout were installed to install large-diameter continuous flight auger (CFA) piles extending down 160 feet.
Excavators and pile crushers prepared a clean foundation floor for the foundation mat pour.